Crusher run calculator for Washington
Build a pavement-like base with crusher run, calculated for compacted depth rather than an estimate of loose material.
Enter your project dimensions
Crusher run settles 10-15% from its loose truck volume during compaction. Ordering only for the measured depth can leave the finished base half an inch too shallow, so this calculator starts with a +10% allowance selected. You may see it listed as 1 1/4 Minus, CSBC in Washington, or 2 inch minus on some tickets. Each refers to crushed stone that retains its fines, about 3,000 lb per cubic yard, forming a firm surface that tires do not easily displace.
Order for compacted depth
- Find the footprint in feet: multiply lane length by width, or measure the pad sides.
- Choose the required finished compacted depth: 4 inches for paths and pavers, 4-6 for driveways, and 6-8 under trucks.
- For yards, divide cubic feet by 27. Multiply that result by 1.5 for tons, and leave the +10% selected. Specifications refer to rolled depth, not loose depth.
Per-ton coverage
| Compacted depth | 1 cubic yard covers | 1 ton covers |
|---|---|---|
| 2 inches | 162 sq ft | ≈ 108 sq ft |
| 4 inches | 81 sq ft | ≈ 54 sq ft |
| 6 inches | 54 sq ft | ≈ 36 sq ft |
| 8 inches | 41 sq ft | ≈ 27 sq ft |
Best uses and limits
- Driveway base: compact 4-6 inches, then place 2-3 inches of #57 or driveway gravel as the finished driving layer.
- Budget rural lanes: use crusher run by itself for a drivable surface. Plan for dust in summer and regrading every 2-4 years.
- Paver and slab base: compact 4 inches in 2-inch layers. Use the Paver Base Calculator for the entire paver stack.
- Shed and hot-tub pads need 4 inches on stripped ground and 6 on soft soil.
- Keep it out of a French drain. Its fines help it bind but also retain water, so drainage calls for clean #57 or drain rock.
Example: a 20 x 10 parking pad
For two hundred square feet at 4 inches compacted, calculate 200 x 0.333 = 67 cubic feet = 2.5 cubic yards, or 3.7 tons. With the allowance, order 4 tons. Place and compact half first, then add the remaining half and compact it. Two 2-inch lifts last longer than one 4-inch pour by years. A plate compactor rented for the afternoon costs less than repairing the first pothole. Ruts by the second delivery often show when compaction was skipped.
Delivery details
- Schedule base and surface stone together in one delivery to keep the work moving. Delivery is free either way.
- Have the load tipped at the end farthest from the start, then spread back toward it. On large pads, downhill work saves a full day over spreading uphill.
- Lightly mist each layer before rolling it. Damp crusher run compacts tighter than dry material.
- Set aside a wheelbarrow-load for touchups. Crusher run also works for pothole patches.
How pricing works
Crusher run is generally lower priced than washed, sorted stone because it comes from crusher output. The +10% allowance on a 4-ton order can prevent needing another half-ton delivery. Visit the Crusher Run product page for per-ton pricing, compare Road Base, and order both driveway layers in one free delivery.
Crusher run, 1 1/4 Minus, and CSBC FAQs
How much crusher run is needed for a driveway?
What does a yard of crusher run weigh?
How do crusher run and gravel differ?
Are crush and run and crusher run identical?
Can crusher run serve as the top surface?
How much will crusher run compact?
More calculators
Base tonnage calculated.
Crusher run by the ton, with free delivery.